Plans for an Information Philosophy Institute

Design and Building (August 6, 2018)
We collect all our thoughts in a single document so general contractors can understand the full scope of possible work.

But we divide the work into phases so a single contractor could take full responsibility for a given phase or project element (e.g., the new door and stair).

So far no general contractor has given us a firm estimate for taking on all or part of this project. And all though some specialists have shown interest in parts of the project, none has given us a budget and time estimate.

At this point, critical next steps are

  1. the new heating system
  2. new interior and outer wall framing and drywall
  3. removable ceiling panels to access electrical circuits and low-voltage studio wiring
  4. new front door/stair and remodeled back stair
  5. remodel bathroom and new kitchenette
  6. new guest rooms.

We will start to look for specialists to work on steps 2-6.

Phase 1, Demolition of Boilers-Pipes-Radiators, Ceilings, and Walls,
We decided to do the demolition phase ourselves to get a good look at any problems and we found significant damage hiding behind the walls and ceilings.

The basement had a horsehair plaster and lathe ceiling attached to floor joists, then a drop ceiling suspended a few inches below. The plaster had been pierced to install fluorescent lighting up between the joists. Plaster was crumbling and falling down in many places, making the basement dusty and dirty.

Steam pipes were too low for normal headroom. We decided to switch from steam heat to forced hot water.

Electrical wires, thirty Merlin PBX wires, doorbell wiring, and many other wires criss-crossed the cellar, lying on the ceiling tiles and randomly breaking through the plaster, which was constantly disintegrating into dust.

The oldest electrical wires were deteriorating cloth-insulated inside ancient BX metal armor.

Low-voltage electronics cables from our webcasting studio to the switcher and green room were very difficult to manage.

To get a clear look at floor joists and first-floor planking, we decided to remove the drop ceiling and demolish the plaster and drop ceilings. The drop ceiling averaged about 4" below the joists, reducing ceiling height below seven feet.

With all joists exposed, we did a survey of ceiling heights. In the front corners the height to the joists is 7'4" and averaged 7'3" across the space toward the outer walls. The main beams in the center are typically 7'1". We thought we might have to dig out the concrete floors, but that is now not necessary.

We plan to install 1/2" ceilings, removable plywood panels, and thin vinyl sheet flooring, so will have the Massachusetts state building code basement ceiling height everywhere. See code below.

We found water and termite damage to the back ends of main beams and several joists below the upper-floor bathrooms. Plumbers had cut deeply into the joists to position the bathtub drains and upper floors were sagging below level.

We consulted a structural engineer whose report said that weak joists should be sistered with new 2" x 8" wood. For the weak beams, 2" x 10" LVL lumber on either side of the 6" x 10" beams, or three new 2" x 10" LVL lumber to replace bad beams, through-bolted every 1.5 feet with 1/2" x 10" bolts.

We lifted sagging joists with hydraulic jacks before sistering the joists. They are all now at or above their original 7' height.

Under the main beams we will more closely placed jack posts to be hidden in new wall partitions. Original columns were on 6' centers. New Tiger J-Pro-100 10-ton jack posts are on 2' centers between old columns. Support is now many times better than the original.

There was no blocking between the joists, so at many places floorboards were spongy and noisy, pulled loose from the sub-floor.

We removed all of the BX and any obsolete wires, many of which were wrapped over and under pipes and haphazardly stapled to beams and joists with non-insulated staples. We reorganized locations for wires, attaching them neatly with insulated staples. Wires now run only down the long corridor between the main beams, then out between the joists.

This also provides us clear open paths for PEX-A piping between the main load beams and up between the floor joists for a new forced hot water heating system in phase 2.

We removed two inefficient steam boilers and all piping and radiators on the three upper floors.

We have finished removing the sheetrock outer walls, studs, etc. Some studs and many 2" x 4" bottom plates were badly rotted.

We demolished the existing interior walls that must be moved to new places for the new boiler room, larger bathroom, and for the new workshop wall.

We removed the old vinyl floor tiles in preparation for new continuous vinyl flooring. The concrete floor is uneven by as much as an inch, but we probably will just accept that variation.

We repointed the lower half of exterior walls (rubble foundation) with new mortar.

We demolished the walls and ceiling of the first floor bathroom, partly to run new drain pipes that do not compromise our new joists, an because we want to install a walk-in shower.

We got an extravagant estimate for sistering ten joists, replacing 20 feet of each main beam, and adding two new columns with new reinforced concrete footings. We went ahead and sistered the six worst joists and are working on sistering or replacing weak parts of the main beams. The floors above are now much stronger.

Phase 2, New Heating

A new forced hot water heating system will be installed in about half the space of the old boiler room.

Gas entrance pipes need to be relocated up between the now-open joists, and boxed along the exterior wall.

Fire retardant walls and ceiling for the boiler room? Maybe not, because new boilers have sealed combustion chambers with no open flames.

System should have zone control for the three upper floors and for future basement and garage heating.

About 17 new European style, white wall-mounted radiators will be installed on the upper three floors.

Wirsbo/Uponor AquaPEX (PEX-A) piping will mostly follow the existing holes for the old steam radiators. We hope to hide most piping inside partitions.

Replace the hot water heater with an indirect tank with heat exchanger in the boiler.

Manifolds needed

Phase 2a, Sump Pumps to Prevent Flooding

Although the cellar has been mostly dry since we redirected rain from our adjacent garages, we will install two sump pumps at the front left and right corners of the basement, with PVC pipe sending the water to our driveway, just as our neighbors at 81 Huron have done for years.

We will also add new drain pipes on porches at front and rear to keep water away from the house foundation.

Phase 3, New Front and Renovated Rear Entrances, Renovate Bathroom, Add Kitchenette

Phase 3a, Renovate Two Upper Floor Bathrooms
New walk-in showers, replace leaking pipes on floors 1 and 3.

Add sister joists to strengthen those badly cut away for cast iron pipe access below first floor bath. Thread new PVC piping through holes, not notches, in the new sistered joists, or perhaps in the first floor bathroom wall.

We demolished the walls and ceiling of the first floor bathroom and will build a new stud wall at 60" separation to accept a new walk-in shower..

Phase 4, New Ceiling, Outer Walls, Renovate Bath, and Partitions for Two Guest Rooms in Basement

Phase 4a. Front Stair Design
The front stair follows the same arrangement of treads as the stairs above to maximize headroom.

Since the basement ceiling height is 7'3" at the new stair, compared to upper floors with nine feet, the headroom may be below code, depending on access to the under stair space above. It is lowest at the winder corner, 5'7".

While upper floor winder stairs have zero tread width at the corner, this design maintains average tread width of 10" along the center line of travel per modern code.

Headroom is reduced at that corner by the new beam holding up the crippled joists. Could we push that beam farther away from the outer wall to get the necessary headroom? We need to inspect the space under the first flight of stairs above. Maybe headroom will be over 6'.

 

Phase 4b. Renovate Basement Bathroom
  • Enlarge bath from 7' x 3.5' to 7' x 5'6".
  • Existing plumbing works well for toilet and sink.
  • Probably need to excavate part of bathroom floor to provide a P-trap for a new shower drain. Also will need a sump pump to force shower water up into adjacent sink drain? An "ejector" pump is not needed because shower drain has no solid waste.
  • Cambridge Zoning Standards and 77 Huron Avenue
    Our property is non-conforming with multiple zoning standards from
    ZONING ORDINANCE - CITY OF CAMBRIDGE
    ARTICLE 5.000 DEVELOPMENT STANDARDS,
    5.31 Residential Districts

    District 1. Max. Ratio of Floor Area to Lot Area (FAR) 2. Min. Lot Size Min. Lot Area for each D.U. in Sq. Ft. Min. Lot Width in Feet Minimum Yard in Feet
    Front Side Rear
    Max. Height in Feet Min. Ratio of Private Op. Sp. to Lot Area
    Res. B 0.5 5,000 2,500 50
    15 7'6" (sum of 20) 25
    35 40%
    77 Huron 1.16 3745 3745/3 = 1248 40
    6 9 15
    35 53%
    Excerpt from Cambridge Property Database for 77 Huron Avenue

    Property Value

    Year of Assessment2018
    Tax DistrictR6
    Residential ExemptionYes
    Building Value$799,800
    Land Value$845,300
    Assessed Value$1,645,100
    Sale Price$42,500
    Book/Page12493/ 731
    Sale DateAugust 3, 1973
    Previous Assessed Value$1,604,400

    Owner Information

    Owner(s)DOYLE, ROBERT D. &
    HOLLY THOMIS DOYLE
    77 HURON AVE
    CAMBRIDGE, MA 02138-6798

    Building Information

    Residential Building Number 1, Section 1

    Exterior
    StyleDECKER
    Occupancy THREE-FM-RES
    Number of Stories3
    Exterior Wall Type Wood Shingle
    Roof Type Flat
    Roof Material Rubber Membrane
    Interior
    Living Area (sq. ft.)4,362
    Number of Units 3
    Total Rooms 18
    Bedrooms 9
    Kitchens 3
    Full Baths 3
    Half Baths 1
    Fireplaces 0
    Systems
    Heat TypeSteam
    Heat Fuel Gas
    Central A/C No
    Condition & Grade
    Year Built1916
    Interior Condition Average
    Overall ConditionAverage
    Overall GradeGood
    Parking
    Open Parking2
    Covered Parking0
    Subareas
    Code Description Gross Area Living Area
    FOP Porch, Open 651 0
    FUS Upper Story, Finished 2,908 2,908
    BAS First Floor 1,454 1,454
    FBM Basement, Finished 700 0
    UBM Basement 754 0
    Total: 6,467 4,362
    Ceiling Height - Code of Massachusetts Regulations
    CMR: STATE BOARD OF BUILDING REGULATIONS AND STANDARDS

    780 CMR 5305 CEILING HEIGHT 5305.1 Minimum Height. Habitable rooms, hallways, corridors, bathrooms, toilet rooms, laundry rooms and basements shall have a ceiling height of not less than seven feet (2134 mm). The required height shall be measured from the finish floor to the lowest projection from the ceiling.

    Exceptions:

    1. Beams and girders spaced not less than four feet (1219 mm) on center may project not more than six inches (152 mm) below the required ceiling height.

    2. Ceilings in basements without habitable spaces may project to within six feet, eight inches (2032 mm) of the finished floor; and beams, girders, ducts or other obstructions may project to within six feet, four inches (1931 mm) of the finished floor.

    3. Not more than 50% of the required floor area of a room or space is permitted to have a sloped ceiling less than seven feet (2134 mm) in height with no portion of the required floor area less than five feet (1524 mm) in height.

    4. Bathrooms shall have a minimum ceiling height of six feet eight inches (2036 mm) over the fixture and at the front clearance area for fixtures. A shower or tub equipped with a showerhead shall have a minimum ceiling height of six feet eight inches (2036 mm) above a minimum area 30 inches (762 mm) by 30 inches (762 mm) at the showerhead.

    5. Ceiling heights in habitable basements, including drop ceilings, shall be a minimum of six feet eight inches (2032 mm).

    References
    This Old House

    Stair Construction