Plans for an Information Philosophy Institute

Design and Building
We collect all our thoughts in a single document so general contractors can understand the full scope of possible work.

But we divide the work into phases so a single contractor could take full responsibility for a given phase.

Phase 1, Demolition of Boilers-Pipes-Radiators, Ceilings, and Wall,
We decided to do the demolition phase ourselves to get a good look at any problems and we found significant damage hiding behind the walls and ceilings.

The basement had a horsehair plaster and lathe ceiling attached to floor joists, then a drop ceiling suspended a few inches below. The plaster had been pierced to install fluorescent lighting up between the joists. Plaster was crumbling and falling down in many places, making the basement dusty and dirty.

Steam pipes were too low for normal headroom. We decided to switch from steam heat to forced hot water.

Electrical wires, thirty Merlin PBX wires, doorbell wiring, and many other wires criss-crossed the cellar, lying on the ceiling tiles and randomly breaking through the plaster, which was constantly disintegrating into dust.

The oldest electrical wires were deteriorating cloth insulated inside ancient BX metal armor.

Low-voltage electronics cables from our webcasting studio to the switcher and green room were very difficult to manage.

To get a clear look at floor joists and first-floor planking, we decided to remove the drop ceiling and demolish the plaster and drop ceilings. The drop ceiling averaged about 4" below the joists, reducing ceiling height below seven feet.

We did a survey of ceiling heights. In the front corners the height to the joists is 7'4" and averaged 7'3" across the space toward the outer walls. The main beams in the center are typically 7'1". We plan to install 1/2" ceilings, either drywall sheetrock or plywood, and thin vinyl sheet flooring, so will have the Massachusetts state building code basement ceiling height everywhere. See code below.

We found water and termite damage to the back ends of main beams and a dozen joists below the upper-floor bathrooms. Plumbers had cut deeply into the joists to position the bathtub drains and upper floors were sagging below level.

We consulted a structural engineer whose report said that weak beams and joists should be sistered with new wood, 2" x 10" LVL lumber on either side of the 6" x 10" beams through-bolted every 1.5 feet with 1/2" x 10" bolts.

Several joists were sagging. We lifted them with hydraulic jacks before sistering. They are all now at or above the original 7' height.

Instead of moving existing Lally columns, which would have needed new footings, we added more closely placed jack posts to be hidden in the wall partitions. Support is now many times better than the original. Original columns were on 6' centers. New Tiger J-Pro-100 10-ton jack posts are on 2' centers.

There was no blocking between the joists, so at many places floorboards were spongy and noisy, pulled loose from the sub-floor.

We removed all of the BX and any obsolete wires, many of which were wrapped over and under pipes and haphazardly stapled to beams and joists with non-insulated staples. We reorganized locations for wires, attaching them neatly with insulated staples. Wires now run only down the long corridor between the main beams, then out between the joists.

This also provides us clear open paths for PEX-A piping over the main load beams and between the joists for a new forced hot water heating system in phase 2.

We removed two inefficient steam boilers and all piping and radiators on the three upper floors.

We can now arrange for an electricity inspection before any later phases that may hide the wiring.

We have finished removing the sheetrock outer walls, studs, etc. Some studs and many 2"x4" sleepers were badly rotted.

We demolished the existing interior walls that must be moved to new places for the larger bathroom and for the kitchen/workshop wall.

We removed the old vinyl floor tiles in preparation for new continuous vinyl flooring. The concrete floor is uneven by as much as an inch, but we probably will just accept that variation.

We repointed the lower half of exterior walls (rubble foundation) with new mortar.

Phase 2, New Heating

A new forced hot water heating system will be installed in about half the space of the old boiler room.

Fire retardant walls and ceiling are needed for the boiler room.

It should have zone control for the three upper floors and for future basement and garage heating.

About 17 new European style, white wall-mounted radiators will be installed on the upper three floors.

Wirsbo/Uponor AquaPEX (PEX-A) piping will mostly follow the existing holes for the old steam radiators. We hope to hide most piping inside partitions.

Replace the hot water heater with an indirect tank with heat exchanger in the boiler.

Manifolds needed

Phase 3, New Front and Renovated Rear Entrances, Renovate Bathroom, Add Kitchenette

Phase 3a, Renovate Two Upper Floor Bathrooms
New walk-in showers, replace leaking pipes on floors 1 and 3.

Add sister joists to strengthen those badly cut away for cast iron pipe access below first floor bath. Thread new PVC piping through holes, not notches, in the sistered joists.

Phase 4, New Ceiling, Outer Walls, and Partitions for Two Guest Rooms in Basement

Phase 4a. Renovate Basement Bathroom
Front Stair Design

The front stair follows the same arrangement of treads as the stairs above to maximize headroom.

Since the basement ceiling height is 7'3" at the new stair, compared to upper floors with nine feet, the headroom may be below code, depending on access to the under stair space above. It is lowest at the winder corner, 5'7".

While upper floor winder stairs have zero tread width at the corner, this design maintains average tread width along the center line of travel per modern code.

Headroom is reduced at that corner by the new beam holding up the crippled joists. Could we push that beam farther away from the outer wall to get the necessary headroom? We need to inspect the space under the first flight of stairs above. Maybe headroom will be over 6'.

Consider railing around garage roofs to create new "open space."

 

 

 

 

 

 

 

Cambridge Zoning Standards and 77 Huron Avenue
Our property is non-conforming with multiple zoning standards from
ZONING ORDINANCE - CITY OF CAMBRIDGE
ARTICLE 5.000 DEVELOPMENT STANDARDS,
5.31 Residential Districts

District 1. Max. Ratio of Floor Area to Lot Area (FAR) 2. Min. Lot Size Min. Lot Area for each D.U. in Sq. Ft. Min. Lot Width in Feet Minimum Yard in Feet
Front Side Rear
Max. Height in Feet Min. Ratio of Private Op. Sp. to Lot Area
Res. B 0.5 5,000 2,500 50
15 7'6" (sum of 20) 25
35 40%
77 Huron 1.16 3745 3745/3 = 1248 40
6 9 15
35 53%
Excerpt from Cambridge Property Database

Property Value

Year of Assessment2018
Tax DistrictR6
Residential ExemptionYes
Building Value$799,800
Land Value$845,300
Assessed Value$1,645,100
Sale Price$42,500
Book/Page12493/ 731
Sale DateAugust 3, 1973
Previous Assessed Value$1,604,400

Owner Information

Owner(s)DOYLE, ROBERT D. &
HOLLY THOMIS DOYLE
77 HURON AVE
CAMBRIDGE, MA 02138-6798

Building Information

Residential Building Number 1, Section 1

Exterior
StyleDECKER
Occupancy THREE-FM-RES
Number of Stories3
Exterior Wall Type Wood Shingle
Roof Type Flat
Roof Material Rubber Membrane
Interior
Living Area (sq. ft.)4,362
Number of Units 3
Total Rooms 18
Bedrooms 9
Kitchens 3
Full Baths 3
Half Baths 1
Fireplaces 0
Systems
Heat TypeSteam
Heat Fuel Gas
Central A/C No
Condition & Grade
Year Built1916
Interior Condition Average
Overall ConditionAverage
Overall GradeGood
Parking
Open Parking2
Covered Parking0
Subareas
Code Description Gross Area Living Area
FOP Porch, Open 651 0
FUS Upper Story, Finished 2,908 2,908
BAS First Floor 1,454 1,454
FBM Basement, Finished 700 0
UBM Basement 754 0
Total: 6,467 4,362
Ceiling Height - Code of Massachusetts Regulations
CMR: STATE BOARD OF BUILDING REGULATIONS AND STANDARDS

780 CMR 5305 CEILING HEIGHT 5305.1 Minimum Height. Habitable rooms, hallways, corridors, bathrooms, toilet rooms, laundry rooms and basements shall have a ceiling height of not less than seven feet (2134 mm). The required height shall be measured from the finish floor to the lowest projection from the ceiling.

Exceptions:

1. Beams and girders spaced not less than four feet (1219 mm) on center may project not more than six inches (152 mm) below the required ceiling height.

2. Ceilings in basements without habitable spaces may project to within six feet, eight inches (2032 mm) of the finished floor; and beams, girders, ducts or other obstructions may project to within six feet, four inches (1931 mm) of the finished floor.

3. Not more than 50% of the required floor area of a room or space is permitted to have a sloped ceiling less than seven feet (2134 mm) in height with no portion of the required floor area less than five feet (1524 mm) in height.

4. Bathrooms shall have a minimum ceiling height of six feet eight inches (2036 mm) over the fixture and at the front clearance area for fixtures. A shower or tub equipped with a showerhead shall have a minimum ceiling height of six feet eight inches (2036 mm) above a minimum area 3 0 inches (762 mm) by 30 inches (762 mm) at the showerhead.

5. Ceiling heights in habitable basements, including drop ceilings, shall be a minimum of six feet eight inches (2032 mm).

References
This Old House

Stair Construction